CONSTRUCTION UPDATE – MARCH 2014

2014 is set to be a very exciting year for DoubleOne 3 as the much anticipated development comes to fruition.

The year is off to a great start with construction progressing well and the structure now topped out at Level 8. Over the past few months, the following works have been completed:

  • Structure complete
  • Power has been connected
  • Apartment windows and glass doors are complete up to Level 6
  • Tiling to bathroom and balconies in all ground and level 1 apartments
  • Walls and ceilings complete in apartments up to Level 6

Works currently underway or programmed for the next couple of months are as follows:

  • Lift installation
  • Painting to commence on all ground and Level 1 apartments
  • Removal of scaffolding and crane
  • Floor finishes throughout
  • Ceilings and partitions throughout Levels 1 to 5
  • Joinery installation throughout Levels 1 to 5